This week, I scanned all the old pictures for the foyer expansion of 1994 so the details about that construction could be seen by Pearce construction. The picture above is of the footing along the west wall of the foyer.

Monday we had a meeting at Pearce Construction to interview Five Star Plumbing to see if they are going to be our plumber and site utilities contractor. Jamie was going to check on their references.

Monday was also the day that I mailed out the request for proposals to the special inspector firms so we could get bids from three different firms. As of today Friday, I have received one proposal by fax.

This week we also received additional comments from the city, the department of public works. Next week, Monday we are going to have a meeting to discuss the response to the city.